The City of West Kelowna will begin construction on a new roundabout at the Gellatly and Carrington Roads intersection in early April.
The city has provided a $1.33 million contract to Double T Dirtworx to construct the roundabout, implement minor in-stream storm improvements to Smith Creek, as well as a three-metre wide multi-use asphalt path from Witt and Boucherie Roads. This will provide connection from Westbank Centre to the waterfront.
This price was below the estimated $2.5 million budget, with 80 per cent covered by development cost charges.
This decision comes after an independent review of the current and future traffic needs for the intersection — including all vehicle types and alternative forms of transportation.
Construction is expected to finish in September.
The Gellatly and Carrington Roads intersection will be closed during the weekdays from 7 a.m. to 6 p.m. It will be open to the public on evenings and weekends. Detours will be put in place for approximately 10 weeks in mid April.
The City of West Kelowna will provide a traffic management plan in the days ahead.