Bullet train billions in red

State auditors say flawed decision-making and poor contract management contributed to billions of dollars in cost overruns and delays in building California's bullet train between Los Angeles and San Francisco.

The audit released Thursday faults the High-Speed Rail Authority for starting limited construction in 2013 before it completed critical planning. That led to numerous contract changes, project delays and cost overruns in what is now projected to be a $77 billion project.

It cites more than $2 billion in contract changes in three active Central Valley projects, and delays that pushed back completion estimates from this year to 2022.

The board says it accepts auditors' recommendations.

The audit comes as Gov. Jerry Brown, a staunch supporter, prepares to give way to governor-elect Gavin Newsom, who has expressed mixed emotions.



More World News

World
140102
London Webcam
Webcam provided by webcams.travel
56309
Recent Trending
139097
Soft 103.9
137395
Castanet Proud Member of RTNDA Canada
137189



140620
137513